Maldives Solar (Alternate POI)
184 MW generation in Scurry, TX · In queue since July 2023 · Proposed COD March 2028
184 MW
Capacity
1
Components
Solar
2y 9m
In Queue
IA Executed
IA Status
Signed Dec 2023
Queue → IA
5 months
IA → COD
4y 3m
Total Duration
5 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-03-20
State
TX
County
Scurry
Region
ERCOT
Developer
Maldives Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 59900 Long Draw - 11318 Scurry County South and 345kV 59905 Faraday - 11318 Scurry County South
Data Source
LBNL + Live