Blossomheath BESS
BetaActiveBatteryERCOTLBNL
300.78 MW storage in Ellis, TX · In queue since May 2023 · Proposed COD November 2026
300.78 MW
Capacity
1
Components
Battery
2y 10m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 6m
Facilities Study50%
Queue EntryMay 26, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-11-28
Project Details
State
TX
County
Ellis
Region
ERCOT
Developer
Taurbeng LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap VENUS SWITCH (#1907) _x0013_ SAM SWITCH (#68090) 345 kV line
Data Source
LBNL
No news available for this project.