Beeman BESS — Project Summary

Queue ID
ERCOT-25INR0397
Capacity
50.18 MW
Technology
Battery
Status
active
Location
Gonzales, TX
Region
ERCOT
Developer
Waelder BESS
IA Status
Facility Study

Beeman BESS

BetaActiveBatteryERCOTLBNL + Live

50.18 MW storage in Gonzales, TX · In queue since April 2023 · Proposed COD May 2027

50.18 MW

Capacity

1

Components

Battery

2y 11m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 1m

Facilities Study50%
Queue EntryApr 19, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-05-15

Project Details

State

TX

County

Gonzales

Region

ERCOT

Developer

Waelder BESS

Utility

Entity

ERCOT

Point of Interconnection

69kV Waelder Substation (7232)

Data Source

LBNL + Live

No news available for this project.