Hinkell BESS — Project Summary

Queue ID
ERCOT-25INR0395
Capacity
78.05 MW
Technology
Battery
Status
active
Location
La Salle, TX
Region
ERCOT
Developer
Reveille BESS
IA Status
Facility Study

Hinkell BESS

BetaActiveBatteryERCOTLBNL + Live

78.05 MW storage in La Salle, TX · In queue since August 2023 · Proposed COD July 2027

78.05 MW

Capacity

1

Components

Battery

2y 7m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 11m

Facilities Study50%
Queue EntryAug 21, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-07-01

Project Details

State

TX

County

La Salle

Region

ERCOT

Developer

Reveille BESS

Utility

Entity

ERCOT

Point of Interconnection

8612 Reveille 138kV

Data Source

LBNL + Live

No news available for this project.