MICOT BESS
BetaActiveBatteryERCOTLBNL
150 MW storage in Montgomery, TX · In queue since March 2023 · Proposed COD May 2025
150 MW
Capacity
1
Components
Battery
3 years
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 2m
Schedule
10 months past proposed COD
Facilities Study50%
Queue EntryMar 27, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-05-30
Project Details
State
TX
County
Montgomery
Region
ERCOT
Developer
UR-Silo DevCo LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 44645 Singleton - 46500 Tomball Ckt 74
Data Source
LBNL
No news available for this project.