Bobcat Cameron BESS
BetaActiveBatteryERCOTLBNL + Live
200.78 MW storage in Cameron, TX · In queue since April 2023 · Proposed COD December 2027
200.78 MW
Capacity
1
Components
Battery
2y 11m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 8m
Facilities Study50%
Queue EntryApr 19, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
TX
County
Cameron
Region
ERCOT
Developer
Bobcat BESS, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
5764 East Rio Hondo Substation 138kV
Data Source
LBNL + Live
No news available for this project.