Zorro BESS
ERCOT-25INR0384BetaActiveBatteryERCOTLBNL + Live
153.69 MW storage in Van Zandt, TX · In queue since March 2023 · Proposed COD August 2026
153.69 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 5m
Facilities Study50%
Queue EntryMar 27, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-08-31
Project Details
State
TX
County
Van Zandt
Region
ERCOT
Developer
UR-Silo DevCo LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138 kV Ben Wheeler (Bus# 6852)
Data Source
LBNL + Live