HappyDogSolar
ERCOT-25INR0382BetaActiveSolarERCOTLBNL + Live
85.54 MW generation in Milam, TX · In queue since June 2023 · Proposed COD April 2027
85.54 MW
Capacity
1
Components
Solar
2y 10m
In Queue
IA Executed
IA Status
Signed Dec 2024
Interconnection Timeline
Queue → IA
1y 6m
IA → COD
2y 4m
Total Duration
1y 6m
Construction75%
Queue EntryJun 7, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementDec 16, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-04-13
Project Details
State
TX
County
Milam
Region
ERCOT
Developer
Rosula Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 3704 Hog Creek Switch _x0013_ 3687 Bell County East Switch
Data Source
LBNL + Live
No news available for this project.