Proteus Vernon Solar SLF
BetaActiveSolarERCOTLBNL + Live
75 MW generation in Wilbarger, TX · In queue since March 2023 · Proposed COD February 2029
75 MW
Capacity
1
Components
Solar
3 years
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
5y 11m
Facilities Study50%
Queue EntryMar 27, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-02-18
Project Details
State
TX
County
Wilbarger
Region
ERCOT
Developer
Vernon Solar and Storage LLC (a Delaware LLC)
Utility
—
Entity
ERCOT
Point of Interconnection
6060 Vernon 138kV
Data Source
LBNL + Live
No news available for this project.