Elan BESS
BetaActiveBatteryERCOTLBNL + Live
202.65 MW storage in Fort Bend, TX · In queue since March 2023 · Proposed COD December 2026
202.65 MW
Capacity
1
Components
Battery
3 years
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 9m
Facilities Study50%
Queue EntryMar 8, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
TX
County
Fort Bend
Region
ERCOT
Developer
Elan BESS, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
42380 Needville 138kV
Data Source
LBNL + Live
No news available for this project.