Echols Creek Storage
BetaActiveBatteryERCOTLBNL
100.57 MW storage in Lamar, TX · In queue since April 2023 · Proposed COD December 2026
100.57 MW
Capacity
1
Components
Battery
2y 11m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 8m
Facilities Study50%
Queue EntryApr 7, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
TX
County
Lamar
Region
ERCOT
Developer
BT Ferguson Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV Hawk Hollow Switch (#11768) and Lamar Blossom Switch (#11770)
Data Source
LBNL
No news available for this project.