Wallie Storage — Project Summary

Queue ID
ERCOT-25INR0361
Capacity
205.4 MW
Technology
Battery
Status
active
Location
Howard, TX
Region
ERCOT
Developer
Wallie Storage, LLC
IA Status
Facility Study

Wallie Storage

BetaActiveBatteryERCOTLBNL

205.4 MW storage in Howard, TX · In queue since March 2023 · Proposed COD September 2027

205.4 MW

Capacity

1

Components

Battery

3 years

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 6m

Facilities Study50%
Queue EntryMar 27, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-09-15

Project Details

State

TX

County

Howard

Region

ERCOT

Developer

Wallie Storage, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 138kV 11324 Leatherwood POD - 1326 Stanton East Switch

Data Source

LBNL

No news available for this project.