Cadet Storage
BetaActiveBatteryERCOTLBNL + Live
104.42 MW storage in Brazos, TX · In queue since May 2023 · Proposed COD April 2026
104.42 MW
Capacity
1
Components
Battery
2y 10m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 11m
Facilities Study50%
Queue EntryMay 22, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-04-01
Project Details
State
TX
County
Brazos
Region
ERCOT
Developer
TX BESS 5, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 69kV 32864 BRYN_ATK69 to 32873 BRYN SHADY
Data Source
LBNL + Live