Cado Storage
BetaActiveBatteryERCOTLBNL + Live
205.51 MW storage in Bexar, TX · In queue since March 2023 · Proposed COD April 2029
205.51 MW
Capacity
1
Components
Battery
3 years
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
6y 1m
Facilities Study50%
Queue EntryMar 13, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-04-06
Project Details
State
TX
County
Bexar
Region
ERCOT
Developer
Cado Storage, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138 kV Line from Braunig East (#5030) to Highland Hills (#5205) Ckt. 1
Data Source
LBNL + Live
No news available for this project.