Butcherbird Solar
BetaActiveSolarERCOTLBNL + Live
116 MW generation in Bell, TX · In queue since December 2023 · Proposed COD February 2027
116 MW
Capacity
1
Components
Solar
2y 3m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 2m
Facilities Study50%
Queue EntryDec 18, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-02-01
Project Details
State
TX
County
Bell
Region
ERCOT
Developer
Butcherbird Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138 kV - Bell County #133 to Bartlett Switch #114
Data Source
LBNL + Live