Clutch City Solar Phase II — Project Summary

Queue ID
ERCOT-25INR0330
Capacity
251.27 MW
Technology
Solar
Status
active
Location
Brazoria, TX
Region
ERCOT
Developer
HZ SOLAR I, LLC
IA Status
Facility Study

Clutch City Solar Phase II

ERCOT-25INR0330BetaActiveSolarERCOTLBNL + Live

251.27 MW generation in Brazoria, TX · In queue since February 2023 · Proposed COD July 2028

251.27 MW

Capacity

1

Components

Solar

3y 2m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 5m

Facilities Study50%
Queue EntryFeb 20, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-07-01

Project Details

State

TX

County

Brazoria

Region

ERCOT

Developer

HZ SOLAR I, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap 138kV 42960 Mustang Bayou _x0013_ 42100 Hudson CKT#04

Data Source

LBNL + Live

No news available for this project.