Clutch City Solar Phase II
ERCOT-25INR0330BetaActiveSolarERCOTLBNL + Live
251.27 MW generation in Brazoria, TX · In queue since February 2023 · Proposed COD July 2028
251.27 MW
Capacity
1
Components
Solar
3y 2m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 5m
Facilities Study50%
Queue EntryFeb 20, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-07-01
Project Details
State
TX
County
Brazoria
Region
ERCOT
Developer
HZ SOLAR I, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV 42960 Mustang Bayou _x0013_ 42100 Hudson CKT#04
Data Source
LBNL + Live