Northington Solar
ERCOT-25INR0319BetaActiveSolarERCOTLBNL + Live
129.81 MW generation in Wharton, TX · In queue since February 2023 · Proposed COD July 2027
129.81 MW
Capacity
1
Components
Solar
3y 2m
In Queue
IA Executed
IA Status
Signed Oct 2024
Interconnection Timeline
Queue → IA
1y 8m
IA → COD
2y 9m
Total Duration
1y 8m
Construction75%
Queue EntryFeb 20, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementOct 2, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-07-15
Project Details
State
TX
County
Wharton
Region
ERCOT
Developer
Northington Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
The 138 kV El Campo (#8102) - Pulsar (#8192) Line; AEP.
Data Source
LBNL + Live