Silver Fox Solar — Project Summary

Queue ID
ERCOT-25INR0318
Capacity
101.2 MW
Technology
Solar
Status
active
Location
Grayson, TX
Region
ERCOT
Developer
Industrial Lima Project LLC
IA Status
Facility Study

Silver Fox Solar

BetaActiveSolarERCOTLBNL

101.2 MW generation in Grayson, TX · In queue since July 2023 · Proposed COD May 2026

101.2 MW

Capacity

1

Components

Solar

2y 8m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2y 10m

Facilities Study50%
Queue EntryJul 31, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-05-31

Project Details

State

TX

County

Grayson

Region

ERCOT

Developer

Industrial Lima Project LLC

Utility

Entity

ERCOT

Point of Interconnection

12677 Haggerty Switch 138kV

Data Source

LBNL

No news available for this project.