Staked Plains BESS
BetaActiveBatteryERCOTLBNL
254.8 MW storage in Lubbock, TX · In queue since March 2023 · Proposed COD June 2028
254.8 MW
Capacity
1
Components
Battery
3 years
In Queue
IA Executed
IA Status
Signed Oct 2024
Interconnection Timeline
Queue → IA
1y 7m
IA → COD
3y 8m
Total Duration
1y 7m
Construction75%
Queue EntryMar 13, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementOct 29, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2028-06-01
Project Details
State
TX
County
Lubbock
Region
ERCOT
Developer
Grand Reserve Energy, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
345kV Dunbar Double Mountain Switch (Bus# 23928)
Data Source
LBNL