IEP Blackhawk — Project Summary

Queue ID
ERCOT-25INR0310
Capacity
100 MW
Technology
Battery
Status
active
Location
Galveston, TX
Region
ERCOT
Developer
IEP Texas Verde II, llc
IA Status
Facility Study

IEP Blackhawk

BetaActiveBatteryERCOTLBNL + Live

100 MW storage in Galveston, TX · In queue since April 2023 · Proposed COD December 2026

100 MW

Capacity

1

Components

Battery

2y 11m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 8m

Facilities Study50%
Queue EntryApr 7, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-01

Project Details

State

TX

County

Galveston

Region

ERCOT

Developer

IEP Texas Verde II, llc

Utility

Entity

ERCOT

Point of Interconnection

38740 Heights Substation 138kV

Data Source

LBNL + Live

No news available for this project.