Wizard BESS — Project Summary

Queue ID
ERCOT-25INR0300
Capacity
150.82 MW
Technology
Battery
Status
active
Location
Galveston, TX
Region
ERCOT
Developer
Wizard Energy Storage, LLC
IA Status
IA Executed

Wizard BESS

ERCOT-25INR0300BetaActiveBatteryERCOTLBNL + Live

150.82 MW storage in Galveston, TX · In queue since March 2023 · Proposed COD March 2026

150.82 MW

Capacity

1

Components

Battery

3y 1m

In Queue

IA Executed

IA Status

Signed Aug 2023

Interconnection Timeline

Queue → IA

5 months

IA → COD

2y 7m

Total Duration

5 months

Schedule

1 months past proposed COD

Construction75%
Queue EntryMar 27, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementAug 21, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-03-11

Project Details

State

TX

County

Galveston

Region

ERCOT

Developer

Wizard Energy Storage, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

To the 138 kV League City Substation (#38920)

Data Source

LBNL + Live

No news available for this project.