Buffalo Prairie Storage — Project Summary

Queue ID
ERCOT-25INR0288
Capacity
313.51 MW
Technology
Battery
Status
active
Location
Robertson, TX
Region
ERCOT
Developer
Buffalo Meadow Energy Center, LLC
IA Status
Facility Study

Buffalo Prairie Storage

BetaActiveBatteryERCOTLBNL + Live

313.51 MW storage in Robertson, TX · In queue since January 2023 · Proposed COD September 2028

313.51 MW

Capacity

1

Components

Battery

3y 2m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 8m

Facilities Study50%
Queue EntryJan 3, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-30

Project Details

State

TX

County

Robertson

Region

ERCOT

Developer

Buffalo Meadow Energy Center, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 345kV 975 Jack Creek - 3400 Twin Oak

Data Source

LBNL + Live