Buffalo Prairie Storage
BetaActiveBatteryERCOTLBNL + Live
313.51 MW storage in Robertson, TX · In queue since January 2023 · Proposed COD September 2028
313.51 MW
Capacity
1
Components
Battery
3y 2m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 8m
Facilities Study50%
Queue EntryJan 3, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-30
Project Details
State
TX
County
Robertson
Region
ERCOT
Developer
Buffalo Meadow Energy Center, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 975 Jack Creek - 3400 Twin Oak
Data Source
LBNL + Live
No news available for this project.