Savannah Oaks Solar
BetaActiveSolarERCOTLBNL + Live
200.97 MW generation in Madison, TX · In queue since January 2023 · Proposed COD September 2028
200.97 MW
Capacity
1
Components
Solar
3y 2m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 8m
Facilities Study50%
Queue EntryJan 3, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-30
Project Details
State
TX
County
Madison
Region
ERCOT
Developer
Savannah Oaks Solar Project LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 46020 Limestone Plant - 967 Gibbons Creek
Data Source
LBNL + Live
No news available for this project.