Hornet Solar II SLF
ERCOT-25INR0282BetaActiveSolarERCOTLBNL + Live
208.95 MW generation in Castro, TX · In queue since January 2023 · Proposed COD July 2028
208.95 MW
Capacity
1
Components
Solar
3y 3m
In Queue
IA Executed
IA Status
Signed Aug 2024
Interconnection Timeline
Queue → IA
1y 7m
IA → COD
3y 11m
Total Duration
1y 7m
Construction75%
Queue EntryJan 3, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementAug 21, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-07-31
Project Details
State
TX
County
Castro
Region
ERCOT
Developer
Hornet Solar II LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Ozark Trail Switch 345kV substation (Bus #23901)
Data Source
LBNL + Live
No news available for this project.