Texas Sage Solar SLF — Project Summary

Queue ID
ERCOT-25INR0275
Capacity
100.7 MW
Technology
Solar
Status
active
Location
Wilson, TX
Region
ERCOT
Developer
Texas Sage Solar Project, LLC
IA Status
Facility Study

Texas Sage Solar SLF

BetaActiveSolarERCOTLBNL

100.7 MW generation in Wilson, TX · In queue since April 2024 · Proposed COD December 2028

100.7 MW

Capacity

1

Components

Solar

1y 11m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 8m

Facilities Study50%
Queue EntryApr 15, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

Project Details

State

TX

County

Wilson

Region

ERCOT

Developer

Texas Sage Solar Project, LLC

Utility

Entity

ERCOT

Point of Interconnection

8193 LYSSY 138kV

Data Source

LBNL

No news available for this project.