Horse Wrangler Storage — Project Summary

Queue ID
ERCOT-25INR0274
Capacity
102.07 MW
Technology
Battery
Status
active
Location
Karnes, TX
Region
ERCOT
Developer
Horse Wrangler Solar Project, LLC
IA Status
Facility Study

Horse Wrangler Storage

BetaActiveBatteryERCOTLBNL

102.07 MW storage in Karnes, TX · In queue since November 2023 · Proposed COD December 2028

102.07 MW

Capacity

1

Components

Battery

2y 4m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 1m

Facilities Study50%
Queue EntryNov 30, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

Project Details

State

TX

County

Karnes

Region

ERCOT

Developer

Horse Wrangler Solar Project, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 138kV 8153 Rosata Tap - 8186 Kenedy Switch Ckt 1

Data Source

LBNL

No news available for this project.