Horse Wrangler Solar
BetaActiveSolarERCOTLBNL
251.33 MW generation in Karnes, TX · In queue since December 2023 · Proposed COD December 2028
251.33 MW
Capacity
1
Components
Solar
2y 3m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5 years
Facilities Study50%
Queue EntryDec 4, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-01
Project Details
State
TX
County
Karnes
Region
ERCOT
Developer
Horse Wrangler Solar Project, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 8153 Rosata Tap (Bus# ) - 8186 Kenedy Switch
Data Source
LBNL