City Breeze BESS — Project Summary

Queue ID
ERCOT-25INR0271
Capacity
140.6 MW
Technology
Battery
Status
active
Location
Matagorda, TX
Region
ERCOT
Developer
City Breeze BESS LLC
IA Status
IA Executed

City Breeze BESS

ERCOT-25INR0271BetaActiveBatteryERCOTLBNL + Live

140.6 MW storage in Matagorda, TX · In queue since December 2022 · Proposed COD March 2027

140.6 MW

Capacity

1

Components

Battery

3y 4m

In Queue

IA Executed

IA Status

Signed May 2024

Interconnection Timeline

Queue → IA

1y 5m

IA → COD

2y 10m

Total Duration

1y 5m

Construction75%
Queue EntryDec 15, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementMay 15, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2027-03-18

Project Details

State

TX

County

Matagorda

Region

ERCOT

Developer

City Breeze BESS LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

8111 MAGILL4A 138KV

Data Source

LBNL + Live

No news available for this project.