East Blackland Battery Storage SLF
BetaActiveBatteryERCOTLBNL + Live
75 MW storage in Travis, TX · In queue since November 2022 · Proposed COD May 2028
75 MW
Capacity
1
Components
Battery
3y 4m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 6m
Facilities Study50%
Queue EntryNov 23, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-05-27
Project Details
State
TX
County
Travis
Region
ERCOT
Developer
DERIVA ENERGY STORAGE, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
7337 Kimbro 138kV
Data Source
LBNL + Live
No news available for this project.