Whiskey BESS
ERCOT-25INR0253BetaActiveBatteryERCOTLBNL + Live
153.72 MW storage in Van Zandt, TX · In queue since December 2022 · Proposed COD July 2027
153.72 MW
Capacity
1
Components
Battery
3y 4m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 7m
Facilities Study50%
Queue EntryDec 7, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-07-31
Project Details
State
TX
County
Van Zandt
Region
ERCOT
Developer
UR-Silo DevCo LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6828 Canton Tap 138 kV
Data Source
LBNL + Live