Strawberry Acres Storage — Project Summary

Queue ID
ERCOT-25INR0248
Capacity
156.73 MW
Technology
Battery
Status
active
Location
Wilson, TX
Region
ERCOT
Developer
Strawberry Acres Energy Center, LLC
IA Status
Facility Study

Strawberry Acres Storage

BetaActiveBatteryERCOTLBNL + Live

156.73 MW storage in Wilson, TX · In queue since November 2022 · Proposed COD September 2028

156.73 MW

Capacity

1

Components

Battery

3y 4m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 10m

Facilities Study50%
Queue EntryNov 23, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-30

Project Details

State

TX

County

Wilson

Region

ERCOT

Developer

Strawberry Acres Energy Center, LLC

Utility

Entity

ERCOT

Point of Interconnection

5132 Eagle Creek Substation 138kV

Data Source

LBNL + Live

No news available for this project.