Bluebonnet Prairie Wind
ERCOT-25INR0247BetaActiveWindERCOTLBNL + Live
173 MW generation in Navarro, TX · In queue since December 2022 · Proposed COD July 2027
173 MW
Capacity
1
Components
Wind
3y 4m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 7m
Facilities Study50%
Queue EntryDec 7, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-07-15
Project Details
State
TX
County
Navarro
Region
ERCOT
Developer
Leeward Renewable Energy Development, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 200 CHATFIELD - 3454 MONTFTSS__8
Data Source
LBNL + Live
Linked EIA Plant
Bluebonnet Prairie Wind
EIA Plant ID: 68082