VALDIVIAN SOLAR
BetaActiveSolarERCOTLBNL + Live
80.45 MW generation in Hunt, TX · In queue since February 2023 · Proposed COD June 2028
80.45 MW
Capacity
1
Components
Solar
3y 1m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 4m
Facilities Study50%
Queue EntryFeb 27, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-06-26
Project Details
State
TX
County
Hunt
Region
ERCOT
Developer
Abei Energy Green III LLC
Utility
—
Entity
ERCOT
Point of Interconnection
138kV 1816 Commerce Switch - 1809 Wolf City
Data Source
LBNL + Live
No news available for this project.