Pato Blanco Storage
BetaActiveBatteryERCOTLBNL + Live
71.34 MW storage in Fort Bend, TX · In queue since May 2023 · Proposed COD March 2026
71.34 MW
Capacity
1
Components
Battery
2y 10m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 10m
Schedule
1 months past proposed COD
Facilities Study50%
Queue EntryMay 15, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-03-01
Project Details
State
TX
County
Fort Bend
Region
ERCOT
Developer
TX BESS 4, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138 kV 44010 W A Parish - 42980 NASH___S02_8
Data Source
LBNL + Live
No news available for this project.