Little Ridge Storage
BetaActiveBatteryERCOTLBNL + Live
252 MW storage in Collin, TX · In queue since May 2023 · Proposed COD December 2025
252 MW
Capacity
1
Components
Battery
2y 10m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 7m
Schedule
4 months past proposed COD
Facilities Study50%
Queue EntryMay 15, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-11
Project Details
State
TX
County
Collin
Region
ERCOT
Developer
TX BESS B LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV Swindell (812) - Olinger (818)
Data Source
LBNL + Live
No news available for this project.