Austin Bayou Storage III — Project Summary

Queue ID
ERCOT-25INR0237
Capacity
150.68 MW
Technology
Battery
Status
active
Location
Brazoria, TX
Region
ERCOT
Developer
Austin Bayou Solar, LLC
IA Status
Facility Study

Austin Bayou Storage III

BetaActiveBatteryERCOTLBNL

150.68 MW storage in Brazoria, TX · In queue since March 2023 · Proposed COD June 2027

150.68 MW

Capacity

1

Components

Battery

3 years

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 3m

Facilities Study50%
Queue EntryMar 8, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-01

Project Details

State

TX

County

Brazoria

Region

ERCOT

Developer

Austin Bayou Solar, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 345kV 43180 Savanna - 43020 Seabreeze Ckt 27 AND 43035 Oasis - 43060 Speedway Ckt 18

Data Source

LBNL

No news available for this project.