SERENGETI SOLAR
ERCOT-25INR0227BetaActiveSolarERCOTLBNL + Live
76.18 MW generation in Delta, TX · In queue since December 2022 · Proposed COD April 2028
76.18 MW
Capacity
1
Components
Solar
3y 4m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 4m
Facilities Study50%
Queue EntryDec 7, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-04-20
Project Details
State
TX
County
Delta
Region
ERCOT
Developer
Abei Energy Green XIV LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV Enloe Tap (bus# 11806) _x0013_ Delta sub (bus# 1802)
Data Source
LBNL + Live
No news available for this project.