Lucy Solar
ERCOT-25INR0225BetaActiveSolarERCOTLBNL + Live
351.3 MW generation in Concho, TX · In queue since June 2023 · Proposed COD June 2027
351.3 MW
Capacity
1
Components
Solar
2y 10m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4 years
Facilities Study50%
Queue EntryJun 28, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-30
Project Details
State
TX
County
Concho
Region
ERCOT
Developer
Concho County Solar 1 LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 7077 Amos Creek - 6444 San Angelo Red Creek and 7077 Amos Creek - 76009 Twin Buttes
Data Source
LBNL + Live
No news available for this project.