Burgos Solar
BetaActiveSolarERCOTLBNL + Live
105.52 MW generation in Milam, TX · In queue since October 2022 · Proposed COD November 2027
105.52 MW
Capacity
1
Components
Solar
3y 5m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 1m
Facilities Study50%
Queue EntryOct 18, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-11-22
Project Details
State
TX
County
Milam
Region
ERCOT
Developer
Twin Oaks Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
3701 Rookie Switch 138 kV
Data Source
LBNL + Live
No news available for this project.