Shadow Ranch Solar
BetaActiveSolarERCOTLBNL + Live
807.61 MW generation in Upton, TX · In queue since September 2022 · Proposed COD June 2026
807.61 MW
Capacity
1
Components
Solar
3y 6m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 9m
Facilities Study50%
Queue EntrySep 27, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-01
Project Details
State
TX
County
Upton
Region
ERCOT
Developer
LectricWind LLC
Utility
—
Entity
ERCOT
Point of Interconnection
842 King Mountain 345kV
Data Source
LBNL + Live
No news available for this project.