Claxton Storage
BetaActiveBatteryERCOTLBNL
75.7 MW storage in Hopkins, TX · In queue since September 2022 · Proposed COD September 2027
75.7 MW
Capacity
1
Components
Battery
3y 6m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5 years
Facilities Study50%
Queue EntrySep 21, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-09-17
Project Details
State
TX
County
Hopkins
Region
ERCOT
Developer
BT Claxton Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV line between Allen Switch (#2514) and Monticello (#1696)
Data Source
LBNL