East West BESS — Project Summary

Queue ID
ERCOT-25INR0202
Capacity
120.96 MW
Technology
Battery
Status
active
Location
Kerr, TX
Region
ERCOT
Developer
East West Energy Storage, LLC
IA Status
Facility Study

East West BESS

ERCOT-25INR0202BetaActiveBatteryERCOTLBNL + Live

120.96 MW storage in Kerr, TX · In queue since October 2022 · Proposed COD March 2027

120.96 MW

Capacity

1

Components

Battery

3y 6m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 5m

Facilities Study50%
Queue EntryOct 6, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-03-18

Project Details

State

TX

County

Kerr

Region

ERCOT

Developer

East West Energy Storage, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

7750 LCRA MOUNTAIN HOME SUB

Data Source

LBNL + Live

No news available for this project.