Veer Energy — Project Summary

Queue ID
ERCOT-25INR0201
Capacity
90.72 MW
Technology
Solar
Status
active
Location
Reeves, TX
Region
ERCOT
Developer
DBR Solar, LLC
IA Status
Facility Study

Veer Energy

BetaActiveSolarERCOTLBNL

90.72 MW generation in Reeves, TX · In queue since December 2022 · Proposed COD December 2026

90.72 MW

Capacity

1

Components

Solar

3y 3m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4 years

Facilities Study50%
Queue EntryDec 7, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

TX

County

Reeves

Region

ERCOT

Developer

DBR Solar, LLC

Utility

Entity

ERCOT

Point of Interconnection

TAP 69kV 38040 IH20 - 38090 Pecos

Data Source

LBNL

No news available for this project.