XE Bonham Solar 1
ERCOT-25INR0199BetaActiveSolarERCOTLBNL + Live
138.4 MW generation in Limestone, TX · In queue since November 2022 · Proposed COD April 2027
138.4 MW
Capacity
1
Components
Solar
3y 5m
In Queue
IA Executed
IA Status
Signed Aug 2024
Interconnection Timeline
Queue → IA
1y 9m
IA → COD
2y 8m
Total Duration
1y 9m
Construction75%
Queue EntryNov 15, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementAug 7, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-04-06
Project Details
State
TX
County
Limestone
Region
ERCOT
Developer
J&J Solar Ranch LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
TAP 138 kV MEXIA_2_1_8 3632 - GROES_SE1_8 3634
Data Source
LBNL + Live
No news available for this project.