Inadale Solar
BetaActiveSolarERCOTLBNL + Live
281.03 MW generation in Scurry, TX · In queue since February 2023 · Proposed COD July 2028
281.03 MW
Capacity
1
Components
Solar
3y 1m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 5m
Facilities Study50%
Queue EntryFeb 20, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-07-25
Project Details
State
TX
County
Scurry
Region
ERCOT
Developer
Inadale Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 kV TONKAWAW_5 (11048) _x0013_ SCURCNTYS_5 (11318) Circuit #2
Data Source
LBNL + Live
No news available for this project.