Palmvalley Storage
BetaActiveBatteryERCOTLBNL + Live
100 MW storage in Hidalgo, TX · In queue since September 2022 · Proposed COD May 2027
100 MW
Capacity
1
Components
Battery
3y 6m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 8m
Facilities Study50%
Queue EntrySep 27, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-05-01
Project Details
State
TX
County
Hidalgo
Region
ERCOT
Developer
Palmvalley Energy Storage LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Frontera (#8980)
Data Source
LBNL + Live
No news available for this project.