Staccato BESS
202.65 MW storage in Fayette, TX · In queue since November 2022 · Proposed COD December 2026
202.65 MW
Capacity
1
Components
Battery
3y 4m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
State
TX
County
Fayette
Region
ERCOT
Developer
Staccato Storage, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
138kV WARDA #7312.
Data Source
LBNL + Live
Neighbors Against Battery Storage Site Appeal Lawsuit
The group of neighbors suing to stop a battery energy storage system (BESS) in Warda are appealing their lawsuit. On May 15, plaintiffs Jim...
McBroom Family Being Sued to Stop Battery Facility
The plaintiffs seek a permanent injunction to stop the construction of a battery energy storage system (BESS) on the McBroom property in Warda.
Last updated 2026-03-26