Triangle Ranch Bravo
BetaActiveWindERCOTLBNL + Live
200.22 MW generation in Cottle, TX · In queue since October 2022 · Proposed COD July 2028
200.22 MW
Capacity
1
Components
Wind
3y 5m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 9m
Facilities Study50%
Queue EntryOct 6, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-07-01
Project Details
State
TX
County
Cottle
Region
ERCOT
Developer
Triangle Ranch Wind
Utility
—
Entity
ERCOT
Point of Interconnection
Edith Clark 345 kV (#60500)
Data Source
LBNL + Live
No news available for this project.