Piedra Solar
300.93 MW generation in Freestone, TX · In queue since September 2022 · Proposed COD December 2026
300.93 MW
Capacity
1
Components
Solar
3y 7m
In Queue
IA Executed
IA Status
Signed Jul 2024
Queue → IA
1y 10m
IA → COD
2y 5m
Total Duration
1y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-12-22
State
TX
County
Freestone
Region
ERCOT
Developer
Piedra Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345-kV line Navarro (68091) _x0013_ Limestone (46020))
Data Source
LBNL + Live