Padrino BESS — Project Summary

Queue ID
ERCOT-25INR0167
Capacity
100.77 MW
Technology
Battery
Status
active
Location
Hill, TX
Region
ERCOT
Developer
Hill Solar II, LLC
IA Status
Facility Study

Padrino BESS

BetaActiveBatteryERCOTLBNL

100.77 MW storage in Hill, TX · In queue since September 2022 · Proposed COD March 2026

100.77 MW

Capacity

1

Components

Battery

3y 6m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 6m

Schedule

0 months past proposed COD

Facilities Study50%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-03-23

Project Details

State

TX

County

Hill

Region

ERCOT

Developer

Hill Solar II, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 345kV 68090 Sam Switch _x0013_ 3389 Fort Smith

Data Source

LBNL

No news available for this project.